Integrated Land Management Plan (ILMP)

Action Plan

Serial 

Objectives 

Project 

Performance Measure

Responsibility 

Delivery Plan  

1 Mil 1 Re-negotiate the Duchy Licence by 2012 Licence in place   DE SMTOD
2 Mil 1 Re-negotiate agreements with commoners to ensure their adherence to military byelaws and, where appropriate, that their livestock can be moved or disturbed by end 2008. All agreements in place with Commoners to enable movement and disturbance of agricultural livestock  SLA  
3 Mil 1 Obtain Natural England consent for the use of BV206 and Viking across DTA  by end 2007 OLD granted SLA Negotiation NE & MOD
4 Mil 5 Update and revise the list of OLD's with Natural England for the SSSI areas of DTA by Oct 07 OLD granted SLA Negotiation NE & MOD
5 Mil 5 Review SOs & modus operandi to fit with partner Job Completed Comdt/ LSS Partnering Agreement
7 Mil 5, EM 2  Reduce litter left in Trg Area by reinforcing waste issues within the briefings for each training unit Reduction year on year of waste collected by Wardens    
6 RLC 1 & 2 Improve Website; Add meteorological data and webcam looking at Yes Tor; add EMS and ILMP; Increase photo library    Monitor both positive and negative feedback. Comdt/HQ DTE  
7 Mil 2 & 4, LS 1 - 4, AR 3 Complete an intervisibility study by Sep 07 to inform an analysis of the visual impact of military infrastructure Study completed SLA  
8 Mil 2 & 4, LS 1 - 4, AR 3 Consider the role of lookouts, their location or relocation (Holming Beam Traiing Area and Range Control).   Agreement with DNPA, within DSG, that all possible measures have been taken SLA/ LSS/ Comdt  
9 Mil 4 & 5, AR 1 Clarify UXO clearance procedures that reduce risk as low as reasonable possible without damaging cultural heritage and natural environment.    Comdt  
10 AR 1 - 3, Mil 4 & 5 Increse public access by reducing the delta between programmed and actual live firing. Reduction of delta by at least 10% Comdt  
11 Mil 5, HE 1 - 4, NC 1 Revisit Cramber Cultural Heritage and Nature Conservation studies completed in 2002/3 in accordance with the conditions of the Cramber Tor planning consent. Meet planning conditions  SLA/ Comdt  
12 Mil 5, NC 1, HE 1 & 4  Produce an Arcview mapping product for DTA to support the management of the training area and planning of military exercises. Layers should include:  Dartmoor Training Area Map, aerial protographyLandholdings Compartments, archaeology, ecologal designations, National vegetation Classification, bird nesting, geology, highways nd byeways, public access routes etc Maps completed   HQ DTE  
13 Mil 4 & 5, AR 2 Design and print a Willsworthy leaflet for a self guided walk including military activities, natural environment and cultural heritage.  Walk leaflets produced  Comdt/EST Public Access ILMP
14 Mil 4, RLC 1  Further reduce risk of uncontrolled fire by participating in Dartmoor Forest Fire Group   Effective co-operation to reduce fire risks and control wild fires  Comdt/ LSS  EMS
15 Mil 4, RLC 1  Implement wildfire control measures including maintaining fire breaks across Willsworthy and fire fighting Effective co-operation to reduce fire risks and in the event of fire  Comdt/ LSS  EMS
16 Mil 5, RLC 1 Support for joint action studies for Dartmoor BAP species, in conjunction with EN, DNPA, RSPB, Duchy of Cornwall.   Number of projects undertaken in partnership; species and habitat benefits.   DE/ Comdt  
17 Mil 3 Okehampton Loop Road. Assist DNPA & Duchy of Cornwall to set policy.  Policy in place SLA/ Comdt  
18 Mil 5, RLC 1, NC 5, 7,  Dartmoor Wader project. Act jointly with Duchy of Cornwall, DNPA, RSPB & EN DTA Participation; Species and habitat benefits   SLA/LSS/ Comdt  
19 Mil 2, NC 6, HE 1, LS 4, EM 2 Continuation of Willsworthy field boundary and historic structures restoration programme (200 m of field boundary/year)  Features restored (numbers/ metres)  SLA/ LSS/ Comdt RDEM
20 Mil 5, EM 2, NC 1 & 4  Commence gorse control at Bagga Tor, 33% in 06/07 and repeat annually until the problem has been resolved  Monitor Area m2 controlled/ year;    SLA/ LSS/ Comdt RDEM
21 Mil 5, EM 2, NC 1 & 4  Japanese Knotweed removal programme from all river corridors within freehold by 2012 Monitor Area m2 controlled/ year;    DE/ LSS/ Comdt RDEM
22 Mil 5, EM 2, NC 1 & 4  Bracken control on hay meadow and species rich grasslands in Willsworthy 07 and repeat until bracken reduced to acceptable levels.  Monitor Area m2 controlled/ year;    DE/ LSS/ Comdt RDEM
23 Mil 5, NC 7 Continue to undertake NVC Phase 2 in 2010 Survey Completed DE/ Comdt  
24 Mil 5, NC 7 Undertake a Bird survey across DTA in 2010 Survey Completed DE/ Comdt  
25 Mil 5, HE 4 Support English Heritage to complete archaeological survey of Cramber Tor in 2007  Survey Completed DE/ Comdt  
26   Undertake a Cultural Heritage Condition Survey of Okehampton in 2010  Survey Completed DE/ Comdt  
27   Undertake a Cultural Heritage Condition Survey of Merrivale in 2010  Survey Completed DE/ Comdt  
28   Undertake a Cultural Heritage Conndition Survey of Wilsworthy 2007 Survey Completed DE/ Comdt  
29   Undertake a Cultural Heritage ConditionSurvey of Ringmoor in 2010 Survey Completed DE/ Comdt  
30 Mil 5, HE 4 Undertake archaeological condition monitoring of designated sites across DTA on established rolling periodic basis.  Survey Completed DE/ Comdt LSS
31 Mil 5, RLC 1 Undertake a noise study of the noise emitted by military training on DTA to be completed in 07   Survey Completed DE/ Comdt SMTOD
32 Mil 1, RLC 2 Undertake a survey of the socio-economic impact of military training upon Dartmoor and surrounding areas Survey Completed 05/06 DE/ Comdt ILMP
33 MIL 1 & Mil 5  Complete desktop assessment of land quality across DTA by the end of 2007 in accordance with MOD Policy Survey Completed DTE, Comdt SMTOD
34 Mil 1 and all others    Complete an Environmental Appraisal of the environmental effects of military training on Dartmoor by Sep 07.   Appraisal Completed DE/ Comdt SMTOD
35 Mil 1 and all others    Publish Cramber Environmental Impact Assessment by end 2007. Planning conditions met SLA/ Comdt ILMP
36 Mil 1 Re-provide Holming Beam Hut in less visually intrusive location by end 2008. Hut completed 08 LSS/ SLA/ Comdt  
37 Mil 2, HE 2, LS 1  Landscape improvements following inter-visibility study Improvements completed 2012 LSS/ DE/ Comdt  
38 Mil 2; Mil 5; HE 2; LS3  Restore Doe Tor linhay as a training feature  Restoration comenced by 07/08 and completed by 09/10 Comdt/ LSS  
39 Mil 2; Mil 5; HE 2; LS3  Restore Bearwalls Farm Cart linhay for use as a training feature  Restoration comenced by 07/08 and completed by 09/10 LSS/ DE/ Comdt  
40 Mil 2; Mil 5; HE 2; LS3  Restore the stock shelter at Standon Farm for training purposes  Restoration comenced by 07/08 and completed by 09/10 LSS/ DE/ Comdt  
41 Mil 1, AR 1, RLC 1 Consider inviting groups of key stakeholders onto the moor to demonstrate and view military training in 07.   Numbers of stakeholders having viewed military training by April 07 DE/ Comdt  
42 Mil 1, AR 1, RLC 1 Increase the public attendance of the Dartmoor Military Heritage Weekend by 100% in 07 % Increase of attendance  DE/ Comdt  
43 Mil 4, EM 2, RLC 1, NR 3  Mitigate any significant hazards of shell crater mires within the peat for large herbivores in 07.    % Reduction of animals bogged down within shell crater mires  SLA  
44 Mil 5, NR 1  Ensure that as the Water Framework Directive is implemented, military training is considered within the forthcomming River Basin Management Plans 07/08  River Catchment Management Plans takes account of the military need.   DE  
45 Mil 5, NR 1 & 3  Assist DNPA research and target restoration work to wet up and restore peat haggs to prevent further peatland deterioration and carbon loss as well as wetting up grassland and moor for breeding waders. Area wetted up m2; NVC change; Breeding wader results    DNPA with support of DTE Dartmoor BAP 
46 Mil 2 Establish a grenade pit at Bagga Tor by end 2008. Completion  LSS/ DE/ Comdt  
47 Mil 5, EM 2, NC 1& 5, W 1, HE 1, 2 & 3, LS 3, NR 1, 2 & 3, AR 1 & 3, RLC 1 & 2   Establish a new briefing video for  troops training on DTA by 08  Completion of Video/  All units to see the video before training commences.  DE/ Comdt  
48 Mil 2, W 2, EM 1 Establish 3ha of new native woodlands at Standon Farm and on MOD freehold as opportunities arise.    Area m2 planted LSS/ DE/ Comdt  
49 Mil 1  Replace Bagga Tor Range Control by end 2007 Completion  LSS/ Comdt/SLA  
50   Restore Wickham target railway Restoration comenced by 07/08 and completed by 09/10 Comdt REES


 

 

 